1. CLECC-Wartsila Finland-BCPP/San Miguel Corp – BESS Project
40MW & 20MW – Limay, Bataan & Toledo Cebu; Erection, Cabling, Testing and Commissioning of 50MVA 69/13.8kV Air Insulated Substation.
2. Schneider Electric Philippines-Meralco Hybrid Substation – Grace Park
10 Ave. Grace Park, Caloocan City, Installation of Medium Voltage 34.5kV 9 Cubicles-Gas Insulated Switchgear, Testing and Commissioning
3. Trends/Semirara-Calaca Power Corporation – PACU Unit 1&2
Bgy San Rafael, Calaca, Batangas, Installation of Low Voltage Main Distribution Panel and Secondary Distribution Panel/ATS (6) Assemblies for Package Air Condition Unit for Power Plant 1&2.